| 1970 - 704 páginas
...by any such order, an equitable adjustment shall be made in the contract price or delivery schedule, or both, and the contract shall be modified in writing...adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change, provided, however,... | |
| United States. Congress. Senate. Committee on Public Works - 1970 - 1660 páginas
...contract shall be iBdified in writing accordingly. Any claim by the Contractor for adjustment "nder this clause must be asserted within thirty (30) days from the date of rn*i"t by the Contractor of the notification of change ; Provided, however. That the Contracting... | |
| 1973 - 344 páginas
...provided for herein, an equitable adjustment shall be made in the contract price or delivery schedule (or both) and the contract shall be modified in writing...adjustment under this clause must be asserted within sixty (60) days from the date of receipt by the Contractor of the notification of change; Provided,... | |
| United States. General Accounting Office - 1973 - 1288 páginas
...any such order, an equitable adjustment shall be made in the contract price or deliver}! schedule, or both, and the contract shall be modified in writing...adjustment under this clause must be asserted within 30 days from the date of receipt by the Contractor of the notification of change, provided, however,... | |
| 1973 - 388 páginas
...as may be so affected, and the contract shall be modified in writing accordingly. Any claim by th« Contractor for adjustment under this clause must be asserted within thirty (30) dayi from the date of receipt by the Contractor of the notification of change; Provided, however, That... | |
| |