" It Is understood and agreed by and between the parties hereto that the work Included In this contract is to be done under the direction of the said Architect, and that his decision as to the true construction and meaning of the drawings and specifications... "
Atlantic Reporter - Página 66
1913
Visualização integral - Acerca deste livro

Wisconsin Reports, Volume 170

Wisconsin. Supreme Court, Frederic King Conover, Frederick William Arthur, Frederick C. Seibold, Arnold LeBell - 1920 - 784 páginas
...the work included in this contract is to be done under the direction of the said architect, and that his decision as to the true construction and meaning of the drawings and specifications shall be final. . . . Tomlinson v. Ashland County, 170 Wis. 58. Should the owner and contractors not...
Visualização integral - Acerca deste livro

The South Western Reporter, Volume 219

1920 - 1274 páginas
...by Owen & I'ayson, architects; that the work was to be done under their direction ; and that their "decision as to the true construction and meaning of the drawings and specifications shall be final." It also provided that the architects were to furnish "such additional drawings and...
Visualização integral - Acerca deste livro

Reports of Cases Decided in the Appellate Court of the State of ..., Volume 67

Indiana. Appellate Court - 1920 - 834 páginas
...the work included in this contract is to be done under the direction of said architects, and their decision as to the true construction and meaning of the drawings and specifications shall be final. "Art. VI. The contractor shall complete the several portions, and the whole of the...
Visualização integral - Acerca deste livro

Reports of Cases Heard and Determined in the Appellate Division ..., Volume 196

New York (State). Supreme Court. Appellate Division - 1921 - 1112 páginas
...included in the contract was to be done under the direction of Saul Bernstein, civil engineer, and that his decision as to the true construction and meaning...of the drawings and specifications should be final. The contract price was $2,650 and .it was provided " that such sum shall be paid by the Owner to the...
Visualização integral - Acerca deste livro

The New York Supplement, Volume 187

1921 - 1042 páginas
...included in the contract was to be done under the direction of Saul Bernstein, civil engineer, and that his decision as to the true construction and meaning...of the drawings and specifications should be final. The contract price was $2,650 and it was provided ; "That such sum shall be paid by the owner to the...
Visualização integral - Acerca deste livro

The Southwestern Reporter, Volume 235

1922 - 1206 páginas
...work to he done by Bostwick was to be done under the direction of Parmelee & Sons, architects, whose decision as to the true construction and meaning of...drawings and specifications should be final ; and that Bostwick should .provide proper facilities at ecuted by W. П. Bostwick and wife to one lall times...
Visualização integral - Acerca deste livro

Practical Accounting for General Contractors

Harris Denison Grant - 1922 - 274 páginas
...the work included in this contract is to be done under the direction of the said Architect, and that his decision as to the true construction and meaning of the drawings and specifications shall be final. It is also understood and agreed by and between the parties hereto that such additional...
Visualização integral - Acerca deste livro

The South Western Reporter, Volume 235

1922 - 1206 páginas
...Bostwick was to be done under the direction of Parmelee & Sons, architects, whose decision as to tlio true construction and meaning of the drawings and specifications should be final ; and that Bostwick should provide proper facilities at all times for the inspection of the work by the college....
Visualização integral - Acerca deste livro

Contractors' Accounting Practice: With Procedure Also for Owners, Architects ...

William Maurice Affelder - 1924 - 408 páginas
...the work included in this contract is to be done under the direction of the said Architect, and that his decision as to the true construction and meaning of the drawings and specifications shall be final. It is also understood and agreed by and between the parties hereto that such additional...
Visualização integral - Acerca deste livro

The Federal Reporter, Volume 234

1916 - 1096 páginas
...work Included In this contract is to be done under the direction of the said architects and that their decision as to the true construction and meaning of the drawings and specifications shall be final. * * » fusal, neglect or failure being certified by the architects, the owners shall...
Visualização integral - Acerca deste livro