| United States. Court of Claims - 1946 - 936 páginas
...calendar day for each day of delay until the work should be completed. Article 9 further provided : * * * the contractor [shall not be] charged with liquidated...God, or of the public enemy, acts of the Government, acts of another contractor in the performance of a contract with the Government, fires, floods, epidemics,... | |
| United States. Court of Claims - 1947 - 806 páginas
...292 Reporter's Statement of the Case Article 9 of the contract provided that the contractor should not be charged with liquidated damages because of...God, or of the public enemy, acts of the Government, acts of another contractor in the performance of a contract with the Government, fires, floods, epidemics,... | |
| United States. Court of Claims, Audrey Bernhardt - 1954 - 1160 páginas
...follows : * * * That the right of the contractor to proceed shall not be terminated or the contractor charged with liquidated damages because of any delays...God, or of the public enemy, acts of the Government, acts of another contractor in the performance of a contract with the Government, fires, floods, epidemics,... | |
| United States. Court of Claims, Audrey Bernhardt - 1955 - 908 páginas
...thereof: Provided, That the right of the contractor to proceed shall not be terminated or the contractor charged with liquidated damages because of any delays...including, but not restricted to, acts of God, or of the pub245 Findings of Fact lie enemy, acts of the Government, acts of another contractor in the performance... | |
| United States. Court of Claims, Audrey Bernhardt - 1952 - 936 páginas
...proceed shall not be terminated or the Contractor charged with liquidated damages because of any delay in the completion of the work due to unforeseeable...God, or of the public enemy, acts of the Government, acts of another contractor in the performance of a contract with the Government, fires, floods, epidemics,... | |
| United States. Court of Claims, Audrey Bernhardt - 1955 - 936 páginas
...the right of the contractor to proceed shall not be terminated under this article or the contractor charged with liquidated damages because of any delays...including, but not restricted to, acts of God, or the public enemy, acts of the Government (including, but not restricted to any preference, priority... | |
| United States. Court of Claims - 1948 - 974 páginas
...That the contractor shall not be charged with liquidated damages or any exo-oS cost when the delay is due to unforeseeable causes beyond the control and...contractor, including but not restricted to, acts of God or the public enemy, acts of the Government, fires, floods, epidemics, quarantine restrictions, strikes,... | |
| United States. Court of Claims - 1948 - 886 páginas
...in the open market or under other contracts when the delay of the contractor in making deliveries is due to unforeseeable causes beyond the control and...including, but not restricted to, acts of God, or the public enemy, acts of the Government, fires, floods, epidemics, quarantine restrictions, strikes,... | |
| United States. Court of Claims, Audrey Bernhardt - 1955 - 1002 páginas
...completion of the work due to unforeseeable causes beyond the control and without the fault or negligence or the contractor, including, but not restricted to,...God, or of the public enemy, acts of the Government, acts of another contractor in the performance of a contract with the Government, fires, floods, epidemics,... | |
| United States. Court of Claims - 1947 - 828 páginas
...excess cost when the delay in delivery is due to unforseeable causes beyond the control and without the fault or negligence of the contractor, including, but not restricted to, acts of God or the public enemy, acts of the Government, fires, floods, epidemics, quarantine restricReporter's Statement... | |
| |