" Art. 3, no claim for delay shall be allowed on account of failure to furnish drawings until two weeks after demand for such drawings and not then unless such claim be reasonable. This Article does not exclude the recovery of damages for delay by either... "
The Architect's Law Manual - Página 205
por Clinton H. Blake (Jr) - 1924 - 253 páginas
Visualização integral - Acerca deste livro

The Law of Architecture and Building: A Consideration of the Mutual Rights ...

Clinton Hamlin Blake - 1916 - 360 páginas
...the work, or by strikes, lockouts, fire, unavoidable casualties or any causes beyond the Contractor's control, or by delay authorized by the Architect pending...drawings and not then unless such claim be reasonable. Art. 36. Owner's Right to Do Work.—If the Contractor should neglect to prosecute the work properly...
Visualização integral - Acerca deste livro

Business Law for Engineers

Calvin Frank Allen - 1917 - 468 páginas
...the work, or by strikes, lockouts, fire, unavoidable casualties or any causes beyond the Contractor's control, or by delay authorized by the Architect pending...drawings and not then unless such claim be reasonable. Art. 36. Owner's Right to Do Work. — If the Contractor should neglect to prosecute the work properly...
Visualização integral - Acerca deste livro

Business Law for Engineers

Calvin Frank Allen - 1917 - 472 páginas
...the work, or by strikes, lockouts, fire, unavoidable casualties or any causes beyond the Contractor's control, or by delay authorized by the Architect pending...drawings and not then unless such claim be reasonable. Art. 36. Owner's Right to Do Work. — If the Contractor should neglect to prosecute the work properly...
Visualização integral - Acerca deste livro

Cyclopedia of Architecture, Carpentry, and Building: A General ..., Volume 6

1917 - 550 páginas
...the work, or by strikes, lockouts, fire, unavoidable casualties or any causes beyond the Contractor's control, or by delay authorized by the Architect pending...drawings, and not then unless such claim be reasonable. Art. 36. Owner's Right to Do Work. — If the Contractor should neglect to prosecute the work properly...
Visualização integral - Acerca deste livro

Business Law for Engineers

Calvin Frank Allen - 1919 - 486 páginas
...fire, unusual delay by common carriers, unavoidable casualties or any causes beyond the Contractor's control, or by delay authorized by the Architect pending...provisions in the contract documents. Art. 36. Owner's Right to Do Work. — If the Contractor should neglect to prosecute the work properly or fail to perform...
Visualização integral - Acerca deste livro

Business Law for Engineers

Calvin Frank Allen - 1919 - 490 páginas
...fire, unusual delay by common carriers, unavoidable casualties or any causes beyond the Contractor's control, or by delay authorized by the Architect pending...39 or other provisions in the contract documents. however, that the Architect shall approve both such action and the amount charged to the Contractor....
Visualização integral - Acerca deste livro

Business Law for Engineers

Calvin Frank Allen - 1919 - 476 páginas
...fire, unusual delay by common carriers, unavoidable casualties or any causes beyond the Contractor's control, or by delay authorized by the Architect pending...39 or other provisions in the contract documents. however, that the Architect shall approve both such action and the amount charged to the Contractor....
Visualização integral - Acerca deste livro

Carpentry and Contracting: A Practical Reference Work on Carpentry ..., Volume 5

1919 - 476 páginas
...the work, or by strikes, lockouts, fire, unavoidable casualties or any causes beyond the Contractor's control, or by delay authorized by the Architect pending...drawings, and not then unless such claim be reasonable. Art. 36. Owner's Right to Do Work.— If the Contractor should neglect to prosecute the work properly...
Visualização integral - Acerca deste livro

The Handbook of Architectural Practice

American Institute of Architects - 1920 - 208 páginas
...fire, unusual delay by common carriers, unavoidable casualties or any causes beyond the Contractor's control, or by delay authorized by the Architect pending...provisions in the contract documents. Art. 36. Owner's Right to Do Work.— If the Contractor should neglect to prosecute the work properly or fail to perform...
Visualização integral - Acerca deste livro

The Handbook of Architectural Practice

American Institute of Architects - 1920 - 212 páginas
...writing to the Architect. In the case of a continuing cause of delay, only one claim is necessary. _ If no schedule is made under Art. 3, no claim for...demand for such drawings and not then unless such claim he reasonable. This article does not exclude the recovery of damages [for. delay by either party under...
Visualização integral - Acerca deste livro