...work called for by this contract within the time(s) specified herein or any extension thereof; or (2) If the Contractor fails to perform any of the other...costs for failure to perform unless the supplies or services to be furnished by the subcontractor were obtainable from other sources In sufficient time... | |
| 1971 - 668 páginas
...contract within the tlme(s) specified herein or any extension thereof; or (2) If the Contractor falls to perform any of the other provisions of this contract,...costs for failure to perform unless the supplies or services to be furnished by the subcontractor were obtainable from other sources in sufficient time... | |
| 1982 - 1316 páginas
...performance of this contract in accordance with its terms, and in either of these two circumstances docs not cure such failure within a period of 10 days (or...the required delivery schedule or other performance requirement!. (d) If this contract is terminated as provided in paragraph (a) of this clause, the Government,... | |
| 1969 - 640 páginas
...perform any of the other provisions of this contract, or so fails to prosecute the work as to endang^r performance of this contract In accordance with its...costs for failure to perform unless the supplies or services to be furnished by the subcontractor were obtainable from other sources in sufficient time... | |
| 1970 - 670 páginas
...contract, or so falls to prosecute the work as to endanger performance of this contract in a:cordance with its terms, and in either of these two circumstances...costs for failure to perform unless the supplies or services to be furnished by the subcontractor were obtainable from other sources in sufficient time... | |
| 1983 - 716 páginas
...shall be liable to the Government for any excess costs of such similar services: Provided, however, That the Contractor shall continue the performance...any excess costs for failure to perform, unless the services to be furnished by the subcontractor were obtainable from other sources in sufficient time... | |
| 1982 - 690 páginas
...shall be liable to the Government for any excess costs of such similar services: Provided, however, That the Contractor shall continue the performance...any excess costs for failure to perform, unless the services to be furnished by the subcontractor were obtainable from other sources in sufficient time... | |
| 1972 - 862 páginas
...Contractor shall be liable to the Government for any excess costs for such similar supplies or services: Provided, That the Contractor shall continue the performance...negligence of either of them, the Contractor shall not be Uabte for any excess costs for failure to perform, unless the supplies or services to be furnished... | |
| 1984 - 720 páginas
...of this contract to the extent not terminated under the provisions of this clause. (c) Except witti respect to defaults of subcontractors, the Contractor...costs for failure to perform unless the supplies or services to be furnished by the subcontractor were obtainable from other sources in sufficient time... | |
| 1977 - 944 páginas
...Contractor. Such causes may Include, but are not restricted to. acts of God or of the public enemy, acta oí the Government In either Its sovereign or contractual...liable for any excess costs for failure to perform, uniese the supplies or services to be furnished by the subcontractor were obtainable from other sources... | |
| |