analysis applied Association axle bars bend test boiler bolts brake bull rings carbon steel cars cent Chicago coal committee conform crank end diameter dimensions driving dynamometer car elastic limit elongation engines equipped finished fire box flange flues forgings fuel gage gauge head end heating surface High-pressure cylinder hose inches iron Item length less loco Low-pressure cylinder machine manganese manufacturer material Mikado Ohio open-hearth process operation packing rings Penna pipe piston rods piston valve PRESIDENT pressure PROPERTIES AND TESTS quenching railroad Recommended Practice rehearing requirements specified rivets road Samples screw Sheet M. M. side rods smokebox Southern Pacific Co specifications specified in Section standard steam stoker superheated superheater superheater locomotives temperature tender tensile strength tension test test specimen tests and inspection thickness threads tion Total tractive tractive effort train truck tubes vanadium weight weld wheels width York City
Passagens conhecidas
Página 438 - The inspector representing the purchaser shall have free entry, at all times while work on the contract of the purchaser is being performed, to all parts of the manufacturer's works which concern the manufacture of the material ordered.
Página 502 - The yield point shall be determined by the drop of the beam of the testing machine.
Página 438 - The manufacturer shall afford the inspector, free of cost, all reasonable facilities to satisfy him that the bars are being furnished in accordance with these specifications. All tests (except check analyses) and inspection shall be made at the place of manufacture prior to shipment, unless otherwise specified, and shall be so conducted as not to interfere unnecessarily with the operation of the works.
Página 494 - Samples tested in accordance with Section 5, which represent rejected material, shall be preserved for two weeks from the date of the test report. In case of dissatisfaction with the results of the tests, the manufacturer may make claim for a rehearing within that time.
Página 494 - The manufacturer shall afford the inspector, without charge, all reasonable facilities to satisfy him that the material is being furnished in accordance with these specifications. All tests (except check analysis) and inspection shall be made at the place of manufacture prior to shipment, unless otherwise specified, and shall be so conducted as not to interfere unnecessarily with the operation of the works.
Página 504 - The purchaser may make the tests to govern the acceptance or rejection of the material in his own laboratory or elsewhere. Such tests, however, shall be made at the expense of the purchaser.
Página 1892 - At each annual meeting the president shall appoint a committee of five whose duty it shall be to report at the next annual meeting subjects for investigation and discussion, and if the subjects are approved by the Association, the president shall appoint special committees to report on them.
Página 557 - Number and capacity. — Every boiler shall be equipped with at least two safety valves, the capacity of which shall be sufficient to prevent, under any conditions of service, an accumulation of pressure more than 5 per cent above the allowed steam pressure.
Página 556 - Handrails and steps for headlights. Switching locomotives with sloping tenders with manhole or headlight located on sloping portion of tender shall be equipped with secure steps and handrail or with platform and handrail leading to such manhole or headlight.
Página 493 - A sufficient discard shall be made from each ingot to secure freedom from injurious piping and undue segregation.