Construction Disputes: Practice Guide with Forms, Volume 1Wolters Kluwer, 01/01/2002 - 1032 páginas All areas of construction litigation are covered in this two-volume set, starting with case analysis, pretrial activities, and special forum issues. The authors continue with an in-depth discussion of the difficult presentation issues for delay and acceleration claims, lost productivity claims, and establishing damages. The final section of the text covers trial and other issues, including direct and cross-examination, appeals, and settlement and releases. Practical examples of, and checklists for, the drafting of many of the key documents used in construction litigation are also included. |
Índice
Initial Client Interview | 1 |
1 | 12 |
Chapter | 13 |
Chapter | 15 |
1 | 19 |
847 | 21 |
08 | 25 |
ALTERNATIVE DISPUTE RESOLUTION 567 | 29 |
13 | 310 |
16 | 316 |
03 | 319 |
19 | 324 |
Elements of Damages | 327 |
9 08 | 348 |
09 | 354 |
Insurance and Bond Claims | 359 |
Chapter 2 | 33 |
Chapter 3 | 35 |
Chapter 19 | 67 |
01 | 78 |
Table of Cases 927 | 79 |
2 06 | 80 |
Form | 97 |
PROJECT DOCUMENTATION | 103 |
03 | 105 |
Risk Analysis | 145 |
Bidding Disputes | 167 |
Changes and Differing Site Conditions | 203 |
Delay and Acceleration Claims | 237 |
Form | 262 |
Loss of Efficiency Claims | 273 |
06 | 294 |
11 | 303 |
04 | 363 |
02 | 364 |
Form 165 Request for Final Decision Previously | 365 |
04 | 370 |
07 | 377 |
16 | 383 |
20 | 390 |
23 | 398 |
05 | 401 |
26 | 406 |
Initiating the Case | 409 |
09 | 412 |
03 | 413 |
05 | 419 |
Form 113 | 427 |
Form 1112 Sample Complaint on Bond | 471 |
Outras edições - Ver tudo
Construction Disputes: Practice Guide with Forms, Volume 1 Thomas J. Kelleher,Brian G. Corgan,William E. Dorris Pré-visualização limitada - 2002 |
Palavras e frases frequentes
acceleration action activities actual additional allowed amount Appeals applicable attorney authority award basis bidder bond breach caused change order claim clause compensation completion considered Constr construction contained contract contractor Corp costs counsel court held damages decision delay determine differing site condition direct documents drawings duty effect efficiency encountered engineering entitled equipment establish estimate event evidence example existing expert extension extra fact failed failure federal give impact increase involved issues labor liability limited loss manager materials method notice obligation obtain owner parties payment performance period plans potential prepared presentation prime contractor problems productivity proposal reasonable records recover recovery request responsible result risk rule schedule specifications statute subcontractor submitted Supp surety termination testimony tion United written