" ... due to unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including, but not restricted to, acts of God, or of the public enemy, acts of the Government, in either its sovereign or contractual capacity, acts... "
Cases Decided in the Court of Claims of the United States - Página 65
por United States. Court of Claims - 1946
Visualização integral - Acerca deste livro

Cases Decided in the Court of Claims of the United States, Volume 111

United States. Court of Claims - 1948 - 886 páginas
...priorities or allocations of equipment or material) , acts of another Contractor in the performance of a contract with the Government, fires, floods,...quarantine restrictions, strikes, freight embargoes, unusually severe weather, or delays of subcontractors or material suppliers due to such causes (unless...
Visualização integral - Acerca deste livro

Decisions of the Comptroller General of the United States, Volume 23

United States. General Accounting Office - 1944 - 1220 páginas
...These it describes as "including, but not restricted to, acts of God, or of the public enemy, acts of the Government, fires, floods, epidemics, quarantine...weather, or delays of subcontractors due to such causes." The purpose of the proviso to protect the contractor against the unexpected, and its grammatical sense...
Visualização integral - Acerca deste livro

The Law of Government Contracts

Robert Preston Shealey - 1927 - 600 páginas
...beyond the control of and without the fault or negligence of the contractor, and including acts of God, quarantine restrictions, strikes, freight embargoes,...unusually severe weather or delays of subcontractors, within which to apply in writing to the contracting officer for extension of time for completing the...
Visualização integral - Acerca deste livro

Treasury Department Appropriation Bill for 1929: Hearing Before the ...

United States. Congress. House. Committee on Appropriations - 1928 - 970 páginas
...of the contractor, including, "but not restricted to. acts of God, or of the public enemy, acts of the Government, fires, floods, epidemics, quarantine...weather or delays of subcontractors due to such causes: Provided, That the contractor shall within ten days from the beginning of any such delay notify the...
Visualização integral - Acerca deste livro

To Establish Uniform Requirements for Government Contracts: Hearing Before ...

United States. Congress. House. Committee on the Judiciary - 1928 - 228 páginas
...negligence of the contractor, including, but not restricted to, acts of God or the public enemy, acts of the Government, fires, floods, epidemics, quarantine...embargoes, and unusually severe weather, or delays of the subcontractors due to such causes." This provision is made known to all bidders and it is assumed,...
Visualização integral - Acerca deste livro

Specifications, Schedule, and Drawings: Hoover Dam, Power Plant and ...

United States. Bureau of Reclamation - 1930 - 132 páginas
...negligence of the contractor, including, but not restricted to, acts of God, or of the public enemy, acts of the Government, fires, floods, epidemics, quarantine...weather or delays of subcontractors due to such causes: Provided further, That the contractor shall within ten days from the beginning of any such delay notify...
Visualização integral - Acerca deste livro

Decisions of the Comptroller General of the United States, Volume 9

United States. General Accounting Office - 1930 - 608 páginas
...negligence of the contractor, including, but not restricted to, acts of God or the public enemy, acts of the Government, fires, floods, epidemics, quarantine...strikes, freight embargoes, and unusually severe weather, but not including delays caused by subcontractors: Provided furthei; That the contractor shall, within...
Visualização integral - Acerca deste livro

To Establish Uniform Requirements for Government Contracts: Hearing Before ...

United States. Congress. House. Committee on the Judiciary - 1930 - 180 páginas
...unforeseeable causes including but not restricted to acts of God, acts of the Government, or the public enemy, fires, floods, epidemics, quarantine restrictions,...strikes, freight embargoes, and unusually severe weather "but not including delays caused by subcontractors" force the Government to purchase needed envelopes...
Visualização integral - Acerca deste livro

The Construction of Hoover Dam: Preliminary Investigations, Design of Dam ...

United States. Department of the Interior, Ray Lyman Wilbur, Elwood Mead - 1933 - 338 páginas
...negligence of the contractor, including, but not restricted to, acts of God, or of the public enemy, acts of the Government, fires, floods, epidemics, quarantine...weather or delays of subcontractors due to such causes: Provided further, That the contractor shall within ten days from the beginning of any such delay notify...
Visualização integral - Acerca deste livro

Orders and Regulations, Corps of Engineers, U.S. Army, 1934

United States. Army. Corps of Engineers - 1934 - 396 páginas
...public enemy, any preference, priority or allocation order issued by the Government or any other act of the Government, fires, floods, epidemics, quarantine...strikes, freight embargoes, and unusually severe weather; and, unless the contracting officer shall determine that the materials or supplies to be furnished...
Visualização integral - Acerca deste livro