" Except as otherwise specifically provided in this contract, all disputes concerning questions of fact arising under this contract shall be decided by the contracting officer subject to written appeal by the contractor within 30 days to the head of the... "
Orders and Regulations, Corps of Engineers, U.S. Army, 1934 - Página 198
por United States. Army. Corps of Engineers - 1934
Visualização integral - Acerca deste livro

Cases Decided in the United States Court of Claims ... with ..., Volume 121

United States. Court of Claims, Audrey Bernhardt - 1952 - 1040 páginas
...concerning questions of fact arising under this contract shall be decided by the contracting officer subject to written appeal by the contractor within 30 days...shall diligently proceed with the work as directed. 12. As a result of the question Bruce had raised at the conference, one of defendant's engineers was...
Visualização integral - Acerca deste livro

Cases Decided in the Court of Claims of the United States, Volume 109

United States. Court of Claims - 1948 - 974 páginas
...questions of fact arising under this contract shall be decided by the contracting officer, subject to written appeal by the contractor within 30 days...meantime the contractor shall diligently proceed with performance. The contract, which specified a discount for prompt payment, and the invitation for bids,...
Visualização integral - Acerca deste livro

Cases Decided in the United States Court of Claims ... with ..., Volume 126

United States. Court of Claims, Audrey Bernhardt - 1954 - 1160 páginas
...concerning questions of fact arising under this contract shall be decided by the contracting officer subject to written appeal by the contractor within 30 days...whose decision shall be final and conclusive upon the parties thereto. In the meantime the contractor shall diligently proceed with the work as directed....
Visualização integral - Acerca deste livro

Cases Decided in the United States Court of Claims ... with ..., Volume 152

United States. Court of Claims, Audrey Bernhardt - 1963 - 938 páginas
...Contracting Officer, subject to written appeal by the Contractor within 30 days to the Secretary of the Navy or his duly authorized representative, whose decision...shall diligently proceed with the work as directed. 6. The specifications, attached to and made a part of the contract, provided that the work would be...
Visualização integral - Acerca deste livro

Cases Decided in the United States Court of Claims ... with ..., Volumes 120-130

United States. Court of Claims, Audrey Bernhardt - 1955 - 1002 páginas
...this contract, all disputes concerning questions of fact arising under this contract shall be decided by the contractor within 30 days to the head of the...whose decision shall be final and conclusive upon the parties thereto. In the meantime the contractor shall diligently proceed with the work as directed....
Visualização integral - Acerca deste livro

Cases Decided in the United States Court of Claims ... with ..., Volume 124

United States. Court of Claims, Audrey Bernhardt - 1953 - 968 páginas
...shall be decided by the Contracting Officer subject to written appeal by the 545 Opinion of the Court Contractor within 30 days to the head of the department...whose decision shall be final and conclusive upon the parties thereto. In the meantime the Contractor shall diligently proceed with the work as directed....
Visualização integral - Acerca deste livro

Cases Decided in the United States Court of Claims ... with ..., Volume 114

United States. Court of Claims, Audrey Bernhardt - 1950 - 824 páginas
...Contracting Officer, subject to written appeal by the Contractor within 30 days to the Secretary of War or his duly authorized representative, whose decision...meantime the Contractor shall diligently proceed with performance. This article thus sets forth the procedure to be followed in the event of disputes arising...
Visualização integral - Acerca deste livro

Cases Decided in the Court of Claims of the United States, Volume 100

United States. Court of Claims - 1944 - 656 páginas
...contracting officer, subject to written appeal by the con100 C. Cls. Reporter's Statement of the Case tractor within 30 days to the head of the department concerned...whose decision shall be final and conclusive upon the parties thereto. In the meantime the contractor shall diligently proceed with the work as directed....
Visualização integral - Acerca deste livro

Cases Decided in the Court of Claims of the United States, Volume 108

United States. Court of Claims - 1947 - 828 páginas
...contract shall be decided by the contracting officer subject to written appeal by the contractor in 30 days to the head of the department concerned or...whose decision shall be final and conclusive upon the parties thereto." Article 21 (b) of the contract provided : (b) The term "contracting officer" as used...
Visualização integral - Acerca deste livro

Cases Decided in the Court of Claims of the United States, Volume 92

United States. Court of Claims - 1941 - 708 páginas
...contract shall be decided by the contracting officer or his duly authorized representative, subject to written appeal by the contractor within 30 days...concerned or his duly authorized representative, whose decisions shall be final and conclusive upon the parties thereto as to such questions. * * * There...