" Government may take over the work and prosecute the same to completion, by contract or otherwise, and the contractor and his sureties shall be liable to the Government for any excess cost occasioned the Government thereby. "
Construction of the District of Columbia Stadium, and Matters Related ... - Página A-52
por United States. Congress. Senate. Committee on Rules and Administration - 1964
Visualização integral - Acerca deste livro

Cases Decided in the United States Court of Claims ... with ..., Volume 121

United States. Court of Claims, Audrey Bernhardt - 1952 - 1040 páginas
...with the work or such part of the work as to which there has been delay. In such event the Government may take over the work and prosecute the same to completion,...contractor and his sureties shall be liable to the Government for any excess cost occasioned the Government thereby. If the contractor's right to proceed...
Visualização integral - Acerca deste livro

Cases Decided in the Court of Claims of the United States, Volume 83

United States. Court of Claims - 1937 - 786 páginas
...contractor refuse or fail to prosecute the work the Government has the right to terminate the contract, take over the work and prosecute the same to completion...and the contractor and his sureties shall be liable for any excess cost occasioned the Government thereby. The second course the Opinion of the Court Government...
Visualização integral - Acerca deste livro

Cases Decided in the United States Court of Claims ... with ..., Volume 132

United States. Court of Claims, Audrey Bernhardt - 1955 - 936 páginas
...with the work or such part of the work as to which there has been delay. In such event the Government may take over the work and prosecute the same to completion,...otherwise, and the contractor and his sureties shall 645 _ Findings of Fact be liable to the Government for any excess cost occasioned the Government thereby....
Visualização integral - Acerca deste livro

Cases Decided in the Court of Claims of the United States, Volume 103

United States. Court of Claims - 1946 - 906 páginas
...with the work or such part of the work as to which there has been delay. In such event the Government may take over the work and prosecute the same to completion,...or otherwise, and the contractor and his sureties (if any) shall be liable to the Government for any excess cost occasioned the Government thereby. If...
Visualização integral - Acerca deste livro

Cases Decided in the United States Court of Claims ... with ..., Volume 138

United States. Court of Claims, Audrey Bernhardt - 1958 - 966 páginas
...with the work or such part of the work as to which there has been delay. In such event the Government may take over the work and prosecute the same to completion, by contract or otherwise, and the contractor and nis sureties shall be liable to the Government for any excess cost occasioned the Government thereby....
Visualização integral - Acerca deste livro

Cases Decided in the United States Court of Claims ... with ..., Volume 116

United States. Court of Claims, Audrey Bernhardt - 1950 - 1004 páginas
...of the work as to which there has been a failure to pay said required wages and prosecute the work to completion by contract or otherwise, and the contractor and his sureties shall be liable to the Government for any excess costs occasioned the Government thereby. ARTICLE 24. Payment and Performance...
Visualização integral - Acerca deste livro

Cases Decided in the Court of Claims of the United States, Volume 98

United States. Court of Claims - 1943 - 906 páginas
...failure to pay said prevailing wages. In such event, it is understood and agreed that the Government may take over the work and prosecute the same to completion by contract or otherwise, and that the contractor and his sureties shall be liable to the Government for any excess cost occasioned...
Visualização integral - Acerca deste livro

Cases Decided in the Court of Claims of the United States, Volume 101

United States. Court of Claims - 1944 - 960 páginas
...to proceed and in this connection the contract provided that the Government might complete the work, by contract or otherwise, "and the contractor and his sureties shall be liable to the Government for any excess cost occasioned the Government thereby." By terminating the contractor's...
Visualização integral - Acerca deste livro

Cases Decided in the Court of Claims of the United States, Volume 111

United States. Court of Claims - 1948 - 886 páginas
...or supplies in the open market or secure the manufacture and delivery of the materials and supplies by contract or otherwise, and the contractor and his sureties shall be liable to the Government thereby; Provided, that the contractor shall not be charged with any excess cost occasioned...
Visualização integral - Acerca deste livro

Cases Decided in the Court of Claims of the United States, Volume 109

United States. Court of Claims - 1948 - 974 páginas
...would insure its completion within the time specified, and that in such event the Government might take over the work and prosecute the same to completion by contract or otherwise, making the contractor and his surety liable to the Government for any excess costs occasioned thereby....
Visualização integral - Acerca deste livro