" Government may take over the work and prosecute the same to completion by contract or otherwise, and the contractor and his sureties shall be liable to the Government for any excess cost occasioned the Government thereby. "
United States Reports: Cases Adjudged in the Supreme Court at ... and Rules ... - Página 99
por United States. Supreme Court - 1945
Visualização integral - Acerca deste livro

Cases Decided in the Court of Claims of the United States, Volume 91

United States. Court of Claims - 1940 - 772 páginas
...Statement of the Case to which there has been delay. In such event, the Government may take over the work and prosecute the same to completion by contract...possession of and utilize in completing the work such material, appliances, and plant as may be on the site of the work and necessary therefor. If the Government...
Visualização integral - Acerca deste livro

Cases Decided in the Court of Claims of the United States, Volume 107

United States. Court of Claims - 1947 - 806 páginas
...such part of the work as to which there has been delay. In such event the Government may take over the work and prosecute the same to completion, by contract...take possession of and utilize in completing the work snch materials, appliances, and plant as may be on the site of the work and necessary therefor. If...
Visualização integral - Acerca deste livro

Cases Decided in the United States Court of Claims ... with ..., Volume 122

United States. Court of Claims, Audrey Bernhardt - 1952 - 936 páginas
...such part of the work as to which there has been delay. In such event the Government may take over the work and prosecute the same to completion, by contract...so terminated, the Government may take possession and utilize in completing the work such materials, appliances, and plant as may be on the site of the...
Visualização integral - Acerca deste livro

Cases Decided in the United States Court of Claims ... with ..., Volume 123

United States. Court of Claims, Audrey Bernhardt - 1958 - 1044 páginas
...such part of the work as to which there has been delay. In such event the Government may take over the work and prosecute the same to completion, by contract...cost occasioned the Government thereby. * * * If the Government does not terminate the right of the Contractor to proceed, the Contractor shall continue...
Visualização integral - Acerca deste livro

Cases Decided in the Court of Claims of the United States, Volume 101

United States. Court of Claims - 1944 - 960 páginas
...to proceed and in this connection the contract provided that the Government might complete the work, by contract or otherwise, "and the contractor and...any excess cost occasioned the Government thereby." By terminating the contractor's right to proceed the Government waived its right to collect the liquidated...
Visualização integral - Acerca deste livro

Cases Decided in the United States Court of Claims ... with ..., Volume 148

United States. Court of Claims, Audrey Bernhardt - 1962 - 784 páginas
...market or secure the manufacture and delivery of the materials and supplies by 49 Finding* of Fact contract or otherwise, and the contractor and his...any excess cost occasioned the Government thereby : * * * 41. Prior to termination of the contract, a representative of CAA, in order to ascertain whether...
Visualização integral - Acerca deste livro

Cases Decided in the United States Court of Claims ... with ..., Volumes 120-130

United States. Court of Claims, Audrey Bernhardt - 1955 - 1002 páginas
...snch part of the work as to which there has been delay. In such event the Government may take over the work and prosecute the same to completion, by contract...contractor and his sureties shall be liable to the Qovernment for any excess cost occasioned the Government thereby. If the contractor's right to proceed...
Visualização integral - Acerca deste livro

Cases Decided in the United States Court of Claims ... with ..., Volume 116

United States. Court of Claims, Audrey Bernhardt - 1950 - 1004 páginas
...of the work as to which there has been a failure to pay said required wages and prosecute the work to completion by contract or otherwise, and the contractor...sureties shall be liable to the Government for any excess costs occasioned the Government thereby. ARTICLE 24. Payment and Performance Bonds. — The contractor...
Visualização integral - Acerca deste livro

Cases Decided in the Court of Claims of the United States, Volume 83

United States. Court of Claims - 1937 - 786 páginas
...or fail to prosecute the work the Government has the right to terminate the contract, take over the work and prosecute the same to completion by contract...and the contractor and his sureties shall be liable for any excess cost occasioned the Government thereby. The second course the Opinion of the Court Government...
Visualização integral - Acerca deste livro

Cases Decided in the Court of Claims of the United States, Volume 104

United States. Court of Claims - 1946 - 936 páginas
...event the original contractor defaulted and the Government completed the work by contract or otherwise, "the contractor and his sureties shall be liable to...any excess cost occasioned the Government thereby." Art. 15 made the decisions of the contracting officer and the head of the Department final on all disputes...
Visualização integral - Acerca deste livro