Contractor , then the time herein fixed for the completion of the work shall be extended for a period equivalent to the time lost by reason of any or all... The Law of Contracts - Página 102por Samuel Williston, Clarence Martin Lewis - 1922Visualização integral - Acerca deste livro
| Illinois. Supreme Court - 1913 - 712 páginas
...contractor is not responsible, or by general strikes or lockouts caused by acts of employees, then the time herein fixed for the completion of the work shall...equivalent to the time lost by reason of any or all the causes aforesaid, which extended period shall be determined and fixed by the architect; but no... | |
| Illinois. Supreme Court - 1908 - 710 páginas
...cyclone, or by abandonment of the work by employees through no fault of the contractor, then the time herein fixed for the completion of the work shall be extended for a period equivalent to the time Iqst by reason of any or all of the causes aforesaid." Article 8 stipulates that the owner shall pay... | |
| United States. Court of Claims, Audrey Bernhardt - 1955 - 908 páginas
...the Contractor, or any other Subcontractor, through no default of the Subcontractor, then the time fixed for the completion of the work shall be extended for a period equivalent to the time lost by any or all of the causes aforesaid, but no such 501 Findings of Fact allowance shall be made unless... | |
| British Columbia - 1913 - 696 páginas
...other unavoidable causes, then the time herein fixed for the doing or completion of any such works shall be extended for a period equivalent to the time...lost by reason of any or all of the causes aforesaid. The period of such extension shall, if the City and Railway Company or the Canadian Northern Railway... | |
| 1907 - 2094 páginas
...earthquake or cyclone, or by strikes or lockouts, through no default of the contractor, then the time herein fixed for the completion of the work shall...the causes aforesaid, but no such allowance shall be claimed or made unless a claim therefor shall be presented in writing to the owner, or Andrew J. Itobinson... | |
| 1914 - 1134 páginas
...architects or of any other contractor employed by the owner on the work, the time fixed for completion "shall be extended for a period equivalent to the...reason of any or all of the causes aforesaid." But It was' also provided that "no such allowance will be made unless a claim thereof is presented in writing... | |
| 1902 - 1270 páginas
...abandonment of the work by the employC-s of the contractor through no fault of theirs, then the time fixed for the completion of the work shall be extended for a period equivalent to the time thus lost," etc. It thus appears that the contractors stipulated what they might claim for themselves... | |
| 1912 - 1356 páginas
...prosecution or completion of the work by the act, neglect, or default of the owner or architect that the time herein fixed for the completion of the work shall be extended for a period equal to the time lost by reason of any such cause. But It also provides that no such allowance shall... | |
| 1907 - 1210 páginas
...no fault of the subcontractor, then the time herein fixed for the completion of the work hereunder shall be extended for a period equivalent to the time...causes aforesaid; but no such allowance shall be made unlesr a claim therefor Is presented in writing to the general contractor within twenty-four hours... | |
| 1915 - 1242 páginas
...resulting from default or collusion on the part of the contractor, then the time herein fixed for (he completion of the work shall be extended for a period...lost by reason of any or all of the causes aforesaid. *• * * " The contractor did employ union labor, as he had agreed to do ; but notwithstanding a strike... | |
| |