Campos ocultos
Livros Livros
" Contractor , then the time herein fixed for the completion of the work shall be extended for a period equivalent to the time lost by reason of any or all... "
The Law of Contracts - Página 102
por Samuel Williston, Clarence Martin Lewis - 1922
Visualização integral - Acerca deste livro

Reports of Cases at Law and in Chancery Argued and Determined in ..., Volume 255

Illinois. Supreme Court - 1913 - 712 páginas
...contractor is not responsible, or by general strikes or lockouts caused by acts of employees, then the time herein fixed for the completion of the work shall...equivalent to the time lost by reason of any or all the causes aforesaid, which extended period shall be determined and fixed by the architect; but no...
Visualização integral - Acerca deste livro

Reports of Cases at Law and in Chancery Argued and Determined in ..., Volume 228

Illinois. Supreme Court - 1908 - 710 páginas
...cyclone, or by abandonment of the work by employees through no fault of the contractor, then the time herein fixed for the completion of the work shall be extended for a period equivalent to the time Iqst by reason of any or all of the causes aforesaid." Article 8 stipulates that the owner shall pay...
Visualização integral - Acerca deste livro

Cases Decided in the United States Court of Claims ... with ..., Volume 131

United States. Court of Claims, Audrey Bernhardt - 1955 - 908 páginas
...the Contractor, or any other Subcontractor, through no default of the Subcontractor, then the time fixed for the completion of the work shall be extended for a period equivalent to the time lost by any or all of the causes aforesaid, but no such 501 Findings of Fact allowance shall be made unless...
Visualização integral - Acerca deste livro

Statutes of the Province of British Columbia

British Columbia - 1913 - 696 páginas
...other unavoidable causes, then the time herein fixed for the doing or completion of any such works shall be extended for a period equivalent to the time...lost by reason of any or all of the causes aforesaid. The period of such extension shall, if the City and Railway Company or the Canadian Northern Railway...
Visualização integral - Acerca deste livro

The Federal Reporter: Cases Argued and Determined in the ..., Volumes 149-150

1907 - 2094 páginas
...earthquake or cyclone, or by strikes or lockouts, through no default of the contractor, then the time herein fixed for the completion of the work shall...the causes aforesaid, but no such allowance shall be claimed or made unless a claim therefor shall be presented in writing to the owner, or Andrew J. Itobinson...
Visualização integral - Acerca deste livro

Atlantic Reporter, Volume 88

1914 - 1134 páginas
...architects or of any other contractor employed by the owner on the work, the time fixed for completion "shall be extended for a period equivalent to the...reason of any or all of the causes aforesaid." But It was' also provided that "no such allowance will be made unless a claim thereof is presented in writing...
Visualização integral - Acerca deste livro

The Southwestern Reporter, Volume 66

1902 - 1270 páginas
...abandonment of the work by the employC-s of the contractor through no fault of theirs, then the time fixed for the completion of the work shall be extended for a period equivalent to the time thus lost," etc. It thus appears that the contractors stipulated what they might claim for themselves...
Visualização integral - Acerca deste livro

The Southwestern Reporter, Volume 147

1912 - 1356 páginas
...prosecution or completion of the work by the act, neglect, or default of the owner or architect that the time herein fixed for the completion of the work shall be extended for a period equal to the time lost by reason of any such cause. But It also provides that no such allowance shall...
Visualização integral - Acerca deste livro

The New York Supplement, Volume 100

1907 - 1210 páginas
...no fault of the subcontractor, then the time herein fixed for the completion of the work hereunder shall be extended for a period equivalent to the time...causes aforesaid; but no such allowance shall be made unlesr a claim therefor Is presented in writing to the general contractor within twenty-four hours...
Visualização integral - Acerca deste livro

The New York Supplement, Volume 150

1915 - 1242 páginas
...resulting from default or collusion on the part of the contractor, then the time herein fixed for (he completion of the work shall be extended for a period...lost by reason of any or all of the causes aforesaid. *• * * " The contractor did employ union labor, as he had agreed to do ; but notwithstanding a strike...
Visualização integral - Acerca deste livro




  1. A minha biblioteca
  2. Ajuda
  3. Pesquisa de livros avançada
  4. Transferir ePub
  5. Transferir PDF