and approved by a person satisfactory to the Architect, and all receipted bills.

He shall at the same time submit to the Architect a complete statement of all moneys properly due for materials or on account of separate contracts, or on account of his fee, or otherwise, which are to be paid direct by the Owner under Article 7 hereof.

The provisions of this Article supersede those of Article 26 of the General Conditions of the Contract.

Article 14. Certificates of Payment

The Architect shall check the Contractor's statements of moneys due, called for in Article 13, and shall promptly issue . certificates to the Owner for all such as he approves, which certificates shall be payable on issuance.

The provisions of this Article supersede the first paragraph of Article 27 of the General Conditions of the Contract.

Article 15. Disbursements

Should the Contractor neglect or refuse to pay, within five days after it falls due, any bill legitimately incurred by him hereunder (and for which he is to be reimbursed under Article 5) the Owner, after giving the Contractor twenty-four hours' written notice of his intention so to do, shall have the right to pay such bill directly, in which event such payment shall not, for the purpose either of reimbursement or of calculating the Contractor's fee, be included in the cost of the work.

Article 16. Termination of Contract

(The provisions of this Article supersede all of Article 37 of the General Conditions of the Contract except the first sentence.)

If the Owner should terminate the contract under the first sentence of Article 37 of the General Conditions of the Contract, he shall reimburse the Contractor for the balance of all payments made by him under Article 5, plus a fee computed upon the cost of the work to date at the rate of percentage

named in Article 4 hereof, or if the Contractor's fee be stated as a fixed sum, the Owner shall pay the Contractor such an amount as will increase the payments on account of his fee to a sum which bears the same ratio to the said fixed sum as the cost of the work at the time of termination bears to a reasonable estimated cost of the work completed, and the Owner shall also pay to the Contractor fair compensation, either by purchase or rental, at the election of the Owner, for any equipment retained. In case of such termination of the contract, the Owner shall further assume and become liable for all obligations, commitments and unliquidated claims that the Contractor may have theretofore, in good faith, undertaken or incurred in connection with said work and the Contractor shall, as a condition of receiving the payments mentioned in this Article, execute and deliver all such papers and take all such steps, including the legal assignment of his contractual rights, as the Owner may require for the purpose of fully vesting in him the rights and benefits of the Contractor under such obligations or commitments.

The Contractor and the Owner for themselves, their successors, executors, administrators and assigns hereby agree to the full performance of the covenants herein contained.

IN WITNESS WHEREOF they have executed this agreement the day and year first above written.

THE STANDARD FORM OF AGREEMENT BETWEEN OWNER AND ARCHITECT

ISSUED BY THE AMERICAN INSTITUTE OF ARCHITECTS FOR USE WHEN A PERCENTAGE OF THE COST OF THE WORK FORMS THE BASIS OF PAYMENT

SECOND EDITION-COPYRIGHT 1917 BY THE AMERICAN INSTITUTE OF ARCHITECTS, WASHINGTON, D. C.

Williston-Secs. 288, 688, 794-798, 1766 and 1966.

THIS AGREEMENT made the..

day of.

.by and between.

in the year Nineteen Hundred and.

hereinafter called the Owner, and .

hereinafter called the Architect,

WITNESSETH, that whereas the Owner intends to erect.

Now, THEREFORE, the Owner and the Architect, for the considerations hereinafter named, agree as follows:

The Architect agrees to perform, for the above-named work, professional services as stated in Article 1 of the "Conditions of Agreement between Owner and Architect," hereinafter set forth.

The Owner agrees to pay the Architect at the rate of....

per cent, hereinafter called the basic rate, computed and payable as stated in the said "Conditions," and to make any other payments and reimbursements arising out of the said "Conditions."

The parties hereto further agree to the following:

CONDITIONS OF AGREEMENT BETWEEN OWNER AND

ARCHITECT

[blocks in formation]

fications growing out of these Conditions of Agreement.

3. Reimbursements.-The Owner is to reimburse the Architect the costs of transportation and living incurred by him and his assistants while travelling in discharge of duties connected with the work, and the costs of the services of heating, ventilating, mechanical, and electrical engineers.

4. Separate Contracts.-The basic rate as hereinbefore defined is to be used when all of the work is let under one contract. Should the Owner determine to have certain portions of the work executed under separate contracts, as the Architect's burden of service, expense, and responsibility is thereby increased, the rate in connec

tion with such portions of the work shall be four per cent greater than the basic rate. Should the Owner determine to have substantially the entire work executed under separate contracts, then such higher rate shall apply to the entire work. In any event, however, the basic rate shall, without increase, apply to contracts for any portions of the work on which the Owner reimburses the Engineer's fees to the Architect, and to the cost of articles not designed by the Architect but purchased under his direction.

5. Extra Services and Special Cases. If after a definite scheme has been approved, the Owner makes a decision which, for its proper execution, involves extra services and expense for changes in or additions to the drawings, specifications or other documents; or if a contract be let by cost of labor and material plus a percentage or fixed sum; or if the Architect is put to labor or expense by delays caused by the Owner or a contractor, or by the delinquency or insolvency of either, or as a result of damage by fire he shall be equitably paid for such extra service. and expense.

Should the execution of any work designed or specified by the Architect, or any part of such work be abandoned or suspended, the Architect is to be paid in accordance with or in proportion to the terms of Article 6 for the service rendered on account of it up to the time of such abandonment or suspension.

6. Payments. Whether the work be executed or whether its execution be suspended or abandoned in part or whole, payments to the Architect on his fee are, subject to the provisions of Article 5, to be made as follows:

Upon completion of the preliminary studies, a sum equal to 20% of the basic rate computed upon a reasonable estimated cost.

Upon completion of specifications and general working drawings (ex

clusive of details) a sum sufficient to increase payments on the fee to 60% of the rate or rates of commission arising from this agreement, computed upon a reasonable cost estimated on such completed specifications and drawings, or if bids have been received, then computed upon the lowest bona fide bid or bids.

From time to time during the execution of work and in proportion to the amount of service rendered by the Architect, payments shall be made until the aggregate of all payments made on account of the fee under this Article, but not including any covered by the provisions of Article 5, shall be a sum equal to the rate or rates of commission arising from this agreement, computed upon the final cost of the work.

Payments to the Architect, other than those on his fee, fall due from time to time as his work is done or as costs are incurred.

No deduction shall be made from the Architect's fee on account of penalty, liquidated damages, or other sums withheld from payments to contractors.

7. The Owner's Decisions.-The Owner shall give thorough consideration to all sketches, drawings, specifications, proposals, contracts, and other documents laid before him by the Architect and, whenever prompt action is necessary, he shall inform the Architect of his decisions in such reasonable time as not to delay the work of the Architect nor to prevent him from giving drawings or instructions to contractors in due season.

8. Survey, Borings, and Tests.— The Owner shall furnish the Architect with a complete and accurate survey of the building site, giving the grades and lines of streets, pavements, and adjoining properties; the rights, restrictions, easements, boundaries, and contours of the building site, and full information as to sewer, water, gas,

and electrical service. The Owner is to pay for borings or test pits and for chemical, mechanical, or other tests when required.

9. Supervision of the Work.-The Architect will endeavor to guard the Owner against defects and deficiencies in the work of contractors, but he does not guarantee the performance of their contracts. The supervision of an architect is to be distinguished from the continuous personal superintendence to be obtained by the employment of a clerk-of-the-works.

When authorized by the Owner, a clerk-of-the-works acceptable to both Owner and Architect shall be engaged by the Architect at a salary satisfactory to the Owner and paid by the Owner, upon presentation of the Architect's monthly certificates.

10. Preliminary Estimates.-When requested to do so, the Architect will make or procure preliminary estimates on the cost of the work and he will endeavor to keep the actual cost of the work as low as may be consistent with the purpose of the building and with proper workmanship and material, but no such estimate can be regarded as other than an approximation.

[ocr errors]

as

11. Definition of the Cost of the Work. -The words "the cost of the work used in Articles 2 and 6 hereof are ordinarily to be interpreted as meaning the total of the contract sums incurred for the execution of the work, not including Architect's and Engineer's fees, or the salary of the Clerk-of-the-Works, but in certain rare cases, e. g., when labor or material is furnished by the Owner below its market cost or when old materials are re-used, the cost of the work is to be interpreted as the cost of all materials and labor necessary to complete the work, as such cost would have been if all materials had been new and if all labor had been fully paid at market prices current when the work was ordered, plus contractor's profits and expenses.

12. Ownership of Documents.Drawings and specifications as instruments of service are the property of the Architect whether the work for which they are made be executed or not.

13. Successors and Assignment.The Owner and the Architect, each binds himself, his successors, executors, administrators, and assigns to the other party to this agreement, and to the successors, executors, administrators, and assigns of such other party in respect of all the covenants of this agreement.

The Architect shall have the right to join with him in the performance of this agreement, any architect or architects with whom he may in good faith enter into partnership relations. In case of the death or disability of one or more partners, the rights and duties of the Architect, if a firm, shall devolve upon the remaining partner or partners or upon such firm as may be established by him or them, and he, they or it shall be recognized as the "successor" of the Architect, and so on until the service covered by the agreement has been performed. The Owner shall have the same rights, but in his case no limitation as to the vocation of those admitted to partnership is imposed.

Except as above, neither the Owner nor the Architect shall assign, sublet or transfer his interest in this agreement without the written consent of the other.

14. Arbitration. All questions in dispute under this agreement shall be submitted to arbitration at the choice of either party.

No one shall be nominated or act as an arbitrator who is in any way financially interested in this contract or in the business affairs of either party.

The general procedure shall conform to the laws of the State in which the work is to be erected. Unless otherwise provided by such laws, the parties may agree upon one arbitrator; other