ditions being as fully a part thereof and hereof as if hereto attached or herein repeated. If anything in the said General Conditions is inconsistent with this Agreement, the Agreement shall govern.

The said documents have been prepared by.. therein and hereinafter called the Architect.

Article 2. Changes in the Work

The Owner, through the Architect, may from time to time, by written instructions or drawings issued to the Contractor, make changes in the above-named Drawings and Specifications, issue additional instructions, require additional work or direct the omission of work previously ordered, and the provisions of this contract shall apply to all such changes, modifications and additions with the same effect as if they were embodied in the original Drawings and Specifications. Since the cost of all such changes is to merge in the final cost of the work, Articles 24 and 25 of the General Conditions of the Contract are annulled, unless elsewhere especially made applicable.

Article 3. The Contractor's Duties and Status

The Contractor recognizes the relations of trust and confidence established between him and the Owner by this Agreement. He covenants with the Owner to furnish his best skill and judgment and to coöperate with the Architect in forwarding the interests of the Owner. He agrees to furnish efficient business administration and superintendence and to use every effort to keep upon the work at all times an adequate supply of workmen and materials, and to secure its execution in the best and soundest way and in the most expeditious and economical manner consistent with the interests of the Owner.

Article 4. Fee for Services

In consideration of the performance of the contract, the Owner agrees to pay the Contractor, in current funds, as comsensation for his services hereunder..

which shall be paid as follows:.

($.

.)

Article 5. Costs to be Reimbursed

The Owner agrees to reimburse the Contractor in current funds all costs necessarily incurred for the proper prosecution of the work and paid directly by the Contractor, such costs to include the following items, and to be at rates not higher than the standard paid in the locality of the work except with prior consent of the Owner:

(a) All labor directly on the Contractor's pay roll.

(b) Salaries of Contractor's Employees stationed at the field office, in whatever capacity employed. Employees engaged, at shops or on the road, in expediting the production or transportation of material, shall be considered as stationed at the field office and their salaries paid for such part of their time as is employed on this work.

(c) The proportion of transportation, traveling and hotel expenses of the Contractor or of his officers or employees incurred in discharge of duties connected with this work.

(d) All expenses incurred for transportation to and from the work of the force required for its prosecution.

(e) Permit fees, royalties, damages for infringement of patents, and costs of defending suits therefor and for deposits lost for causes other than the Contractor's negligence.

(f) Losses and expenses, not compensated by insurance or otherwise, sustained by the Contractor in connection with the work, provided they have resulted from causes other than the fault or neglect of the Contractor. Such losses shall include settlements made with the written consent and approval of the Owner. No such losses and expenses shall be included in the cost of the work for the purpose of determining the Contractor's fee, but if, after a loss from fire, flood or similar cause not due to the fault or neglect of the Contractor, he be put in charge of reconstruction, he shall be paid for his services a fee proportionate to that named in Article 4 hereof.

(9) Minor expenses, such as telegrams, telephone service, expressage, and similar petty cash items.

(h) Cost of hand tools, not owned by the workmen, canvas and tarpaulins, consumed in the prosecution of the work, and depreciation on such tools, canvas and tarpaulins used but not

consumed and which shall remain the property of the Contractor.

Article 6. Costs Not to be Reimbursed.

Reimbursement of expenses to the Contractor shall not include any of the following:

(a) Salary of the Contractor, if an individual, or salary of any member of the Contractor, if a firm, or salary of any officer of the Contractor, if a corporation.

(b) Salary of any person employed, during the execution of the work, in the main office or in any regularly established branch office of the Contractor.

(c) Overhead or general expenses of any kind, except as these may be expressly included in Article 5.

(d) Interest on capital employed either in plant or in expenditures on the work, except as may be expressly included in Article 5.

Article 7. Costs to be Paid Direct by the Owner

In addition to items of cost noted in Article 5 for which the Owner reimburses the Contractor, the Owner shall pay all costs as follows:

(a) Materials, supplies, equipment and transportation required for the proper execution of the work, which shall include all temporary structures and their maintenance; all such costs to be at rates not higher than the standard paid in the locality of the work except with prior consent of the Owner.

(b) The amounts of all separate contracts.

(c) Premiums on all bonds and insurance policies called for under Articles 19, 20, 21 and 22 of the General Conditions of the Contract.

(d) Rentals of all construction plant or parts thereof, whether rented from the Contractor or others, in accordance with rental agreements approved by the Architect. Transportation of said

construction plant, costs of loading and unloading, cost of installation, dismantling and removal thereof and minor repairs and replacements during its use on the work,-all in accordance with the terms of the said rental agreements.

Article 8. Discounts, Rebates, Refunds

All discounts, rebates and refunds, and all returns from sale of surplus materials, equipment, etc., shall accrue to the Owner, and the Contractor shall make provisions so that they can be secured.

Article 9. Contractor's Financial Responsibility

Any cost due to the negligence of the Contractor or anyone directly employed by him, either for the making good of defective work, disposal of material wrongly supplied, making good of damage to property, or excess costs for material or labor, or otherwise, shall be borne by the Contractor, and the Owner may withhold money due the Contractor to cover any such cost already paid by him as part of the cost of the work.

This article supersedes the provisions of Articles 13, 14 and 16 of the General Conditions of the Contract so far as they are inconsistent herewith.

Article 10. Separate Contracts

All portions of the work that the Contractor's organization has not been accustomed to perform or that the Owner may direct, shall be executed under separate contracts let by the Owner direct. In such cases either the Contractor shall ask for bids from contractors approved by the Architect and shall deliver such bids to him, or the Architect shall procure such bids himself, and in either case the Architect shall determine, with the advice of the Contractor and subject to the approval of the Owner, the award and amount of the accepted bid. The Owner shall contract for such work direct with such approved bidders in accordance with the terms of this agreement and the General Conditions of the Contract, which Conditions shall, for the

purposes of such contracts, stand as printed or written and not be subject to the modifications set forth herein.

The Contractor, being fully responsible for the general management of the building operation, shall have full directing authority over the execution of the separate contracts.

The separate Contractors shall not only coöperate with each other, as provided in Article 41 of the General Conditions of the Contract, but they shall conform to all directions of the Contractor in regard to the progress of the work.

Article 11. Title to the Work

The title of all work completed and in course of construction and of all materials on account of which any payment has been made, and materials to be paid for under Article 7, shall be in the Owner.

Article 12. Accounting, Inspection, Audit

The Contractor shall check all material and labor entering into the work and shall keep such full and detailed accounts as may be necessary to proper financial management under this Agreement and the system shall be such as is satisfactory to the Architect or to an auditor appointed by the Owner. The Architect, the auditor and their timekeepers and clerks shall be afforded access to the work and to all the Contractor's books, records, correspondence, instructions, drawings, receipts, vouchers, memoranda, etc., relating to this contract, and the Contractor shall preserve all such records for a period of two years after the final payment hereunder.

Article 13. Applications for Payment

The Contractor shall, between the first and seventh of each month, deliver to the Architect a statement, sworn to if required, showing in detail and as completely as possible all moneys paid out by him on account of the cost of the work during the previous month for which he is to be reimbursed under Article 5 hereof, with original pay rolls for labor, checked