Subcontractor, upon the issuance of certificates, if issued otherwise than as in (e), so that at all times his total payments shall be as large in proportion to the value of the work done by him as the total amount certified to the Contractor is to the... The Law of Architecture and Building - Página 310por Clinton H. Blake (Jr) - 1925 - 349 páginasVisualização integral - Acerca deste livro
| Calvin Frank Allen - 1917 - 472 páginas
...by him as the total amount certified to the Contractor is to the value of the work done by him. (g) To pay the Subcontractor to such extent as may be...fixed in place, less the retained percentage, at the tune the certificate should issue, even though the Architect fails to issue it for any cause not the... | |
| Calvin Frank Allen - 1919 - 490 páginas
...by him as the total amount certified to the Contractor is to the value of the work done by him. (g) To pay the Subcontractor to such extent as may be...fixed in place, less the retained percentage, at the tune the certificate should issue, even though the Architect fails to issue it for any cause not the... | |
| Calvin Frank Allen - 1919 - 476 páginas
...by him as the total amount certified to the Contractor is to the value of the work done by hi™ (g) To pay the Subcontractor to such extent as may be...Subcontractor on demand for his work or materials as far as esecuted and fixed in place, less the retained percentage, at the time the certificate should issue,... | |
| American Institute of Architects - 1920 - 208 páginas
...by him as the total amount certified to the Contractor is to the value of the work done by him. (g) To pay the Subcontractor to such extent as may be...provides for earlier or larger payments than the above. (/O To pay the Subcontractor on demand for his work or materials as far as executed and fixed in place,... | |
| American Institute of Architects - 1920 - 212 páginas
...or the Subcontract, if either of these provides for earlier or larger payments than the above. (A) To pay the Subcontractor on demand for his work or materials as far as executed and fixed in place, lest the retained percentage, at the time the certificate should issue, even though the Architect fails... | |
| Samuel Williston, Clarence Martin Lewis - 1922 - 752 páginas
...by him as the total amount certified to the Contractor is to the value of the work done by him. (g) To pay the Subcontractor to such extent as may be...these provides for earlier or larger payments than those above. (h) To pay the Subcontractor on demand for his work or materials as far as executed and... | |
| Clinton H. Blake (Jr) - 1924 - 264 páginas
...by him as the total amount certified to the Contractor is to the value of the work done by him. (g) To pay the Subcontractor to such extent as may be...provides for earlier or larger payments than the above. (/*) To pay the Subcontractor on demand for his work or materials as far as executed and fixed in place,... | |
| Theodore Crane - 1927 - 718 páginas
...by him as the total amount certified to the Contractor is to the value of the work done by him. (g) To pay the Subcontractor to such extent as may be...provides for earlier or larger payments than the above. Section 6, (h) To pay the Subcontractor on demand for his work or materials as far as executed and... | |
| Lebert Howard Weir, National Recreation Association - 1928 - 552 páginas
...by him as the total amount certified to the contractor is to the value of the work done by him. (d) To pay the subcontractor on demand for his work or...place, less the retained percentage at the time the certificates should issue, even though the engineer fails to issue for any cause not the fault of the... | |
| Charles Francis Dingman - 1928 - 240 páginas
...by him as the total amount certified to the contractor is to the value of the work done by him. g. To pay the subcontractor to such extent as may be provided by the contract documentor the subcontract, if either of these provides for earlier or larger payments than the above.... | |
| |