Annual Report of the Secretary of War, Volume 2 |
No interior do livro
Resultados 1-3 de 80
Página 172
The other , or east jetty , foundation course is now 14,410 feet in length , measured from the shore end , and is prac tically completed up to high - water level for 14,100 feet of this length . All the work during the past year has ...
The other , or east jetty , foundation course is now 14,410 feet in length , measured from the shore end , and is prac tically completed up to high - water level for 14,100 feet of this length . All the work during the past year has ...
Página 237
The total amount expended to June 30 , 1888 , is $ 47,778.86 , resulting in the building of two piers , the north pier 1,603 feet and the south one 2,151 feet in length , the latter being the full length contemplated by the approved ...
The total amount expended to June 30 , 1888 , is $ 47,778.86 , resulting in the building of two piers , the north pier 1,603 feet and the south one 2,151 feet in length , the latter being the full length contemplated by the approved ...
Página 647
... making a total length of 5,705 feet ; the channel through the shoal in the bay had been dredged to the required dimensions , as also the channel up the river as far as the Newark and New York Railroad Bridge .
... making a total length of 5,705 feet ; the channel through the shoal in the bay had been dredged to the required dimensions , as also the channel up the river as far as the Newark and New York Railroad Bridge .
Opinião das pessoas - Escrever uma crítica
Não foram encontradas quaisquer críticas nos locais habituais.
Índice
OFFICERS OF THE CORPS OF ENGINEERS | 3 |
GENERAL DISCUSSION | 9 |
Officers in charge of divisions 319 | 10 |
72 outras secções não apresentadas
Outras edições - Ver tudo
Palavras e frases frequentes
12 feet 1890 Submitted act of August adopted Amount appropriated amount available Amount estimated amount expended Appendix appropriated by act August 11 available for fiscal breakwater Bridge building canal channel close commerce completion of existing compliance with requirements Congress construction continuing contract Creek dams depth dike distance dredging ending June 30 entrance estimated cost examination exclusive of liabilities existing project expended during fiscal expended in fiscal expended to June expenditure feet at low feet at mean feet deep fiscal year ending funds further harbor acts improvement increased Island jetty Lake length liabilities outstanding July locks low-water mean low water miles mouth navigation object obstructions obtaining operations outstanding liabilities placed Point present project profitably expended proposed removal repairs required for completion requirements of sections resulted river and harbor rock shoals snags Submitted in compliance survey tion vessels width