Annual Report of the Secretary of War, Volume 2 |
No interior do livro
Resultados 1-3 de 91
Página 65
The estimated cost of this was $ 34,200 , of which $ 16,000 had been appropriated up to June 30 , 1886 . After some correspondence and delay the new outlet was excavated and protected on the north side by a bulkhead built partly by the ...
The estimated cost of this was $ 34,200 , of which $ 16,000 had been appropriated up to June 30 , 1886 . After some correspondence and delay the new outlet was excavated and protected on the north side by a bulkhead built partly by the ...
Página 168
July 1 , 1888 , amount expended during fiscal year , exclusive of liabilities outstanding July 1 , 1887 . ... Amount appropriated by act of August 11 , 1888 .. Amount available for fiscal year ending June 30 , 1889 .
July 1 , 1888 , amount expended during fiscal year , exclusive of liabilities outstanding July 1 , 1887 . ... Amount appropriated by act of August 11 , 1888 .. Amount available for fiscal year ending June 30 , 1889 .
Página 190
July 1 , 1887 , amount available .. $ 606.89 July 1 , 1888 , amount expended during fiscal year , exclusive of liabilities outstanding July 1 , 1887 ... 606,89 Amount appropriated by act of August 11 , 1888 .
July 1 , 1887 , amount available .. $ 606.89 July 1 , 1888 , amount expended during fiscal year , exclusive of liabilities outstanding July 1 , 1887 ... 606,89 Amount appropriated by act of August 11 , 1888 .
Opinião das pessoas - Escrever uma crítica
Não foram encontradas quaisquer críticas nos locais habituais.
Índice
OFFICERS OF THE CORPS OF ENGINEERS | 3 |
GENERAL DISCUSSION | 9 |
Officers in charge of divisions 319 | 10 |
72 outras secções não apresentadas
Outras edições - Ver tudo
Palavras e frases frequentes
12 feet 1890 Submitted act of August adopted Amount appropriated amount available Amount estimated amount expended Appendix appropriated by act August 11 available for fiscal breakwater Bridge building canal channel close commerce completion of existing compliance with requirements Congress construction continuing contract Creek dams depth dike distance dredging ending June 30 entrance estimated cost examination exclusive of liabilities existing project expended during fiscal expended in fiscal expended to June expenditure feet at low feet at mean feet deep fiscal year ending funds further harbor acts improvement increased Island jetty Lake length liabilities outstanding July locks low-water mean low water miles mouth navigation object obstructions obtaining operations outstanding liabilities placed Point present project profitably expended proposed removal repairs required for completion requirements of sections resulted river and harbor rock shoals snags Submitted in compliance survey tion vessels width