" ... unforeseeable causes beyond the control and without the fault or negligence of the contractor, including, but not restricted to, acts of God, or of the public enemy, acts of the Government, acts of another contractor in the performance of a contract... "
Decisions of the Comptroller General of the United States - Página 511
por United States. General Accounting Office - 1968
Visualização integral - Acerca deste livro

Cases Decided in the Court of Claims of the United States, Volume 84

United States. Court of Claims - 1937 - 710 páginas
...due to unforeseeable causes beyond the control and without the fault or negligence of the contractor, including, but not restricted to, acts of God or of...strikes, freight embargoes, and unusually severe weather, but not including delays caused by subcontractors : Provided further. That the contractor shall within...
Visualização integral - Acerca deste livro

Cases Decided in the Court of Claims of the United States, Volume 98

United States. Court of Claims - 1943 - 906 páginas
...due to unforseeable causes beyond the control and without the fault or negligence of the contractor, including, but not restricted to, acts of God, or...restrictions, strikes, freight embargoes, and unusually Reporter's Statement of the Case severe weather or delays of subcontractors due to such causes: Provided...
Visualização integral - Acerca deste livro

Cases Decided in the United States Court of Claims ... with ..., Volume 122

United States. Court of Claims, Audrey Bernhardt - 1952 - 936 páginas
...due to unforeseeable causes beyond the control and without the fault or negligence of the contractor, Including, but not restricted to, acts of God or of...quarantine restrictions, strikes, freight embargoes, unusually severe weather, and delays of a subcontractor due to such causes unless the contracting officer...
Visualização integral - Acerca deste livro

Cases Decided in the United States Court of Claims ... with ..., Volume 152

United States. Court of Claims, Audrey Bernhardt - 1963 - 938 páginas
...beyond the control and without the fault or negligence of the Contractor. Such causes include, but are not restricted to, acts of God or of the public enemy,...quarantine restrictions, strikes, freight embargoes, unusually severe weather, and defaults of subcontractors due to any of Findings of Fact such causes...
Visualização integral - Acerca deste livro

Cases Decided in the Court of Claims of the United States, Volume 101

United States. Court of Claims - 1944 - 960 páginas
...public enemy, acts of the Government, acts of another contractor in the performance of a contract with the Government, fires, floods, epidemics, quarantine...weather or delays of subcontractors due to such causes, if the contractor shall within 10 days from the beginning of any such delay (unless the contracting...
Visualização integral - Acerca deste livro

Cases Decided in the United States Court of Claims ... with ..., Volumes 120-130

United States. Court of Claims, Audrey Bernhardt - 1955 - 1002 páginas
...public enemy, acts of the Government, acts of another contractor In the performance of a contract with the Government, fires, floods, epidemics, quarantine...severe weather or delays of subcontractors due to snch causes, if the contractor shall within 10 days from the beginning of any such delay (unless the...
Visualização integral - Acerca deste livro

Cases Decided in the United States Court of Claims ... with ..., Volume 121

United States. Court of Claims, Audrey Bernhardt - 1952 - 1040 páginas
...preference, priority or allocation order, acts of another contractor in the performance of a contract with the Government, fires, floods, epidemics, quarantine...unusually severe weather or delays of subcontractors clue to such causes, if the contractor shall within 10 days from the beginning of any such delay (unless...
Visualização integral - Acerca deste livro

Cases Decided in the United States Court of Claims ... with ..., Volume 126

United States. Court of Claims, Audrey Bernhardt - 1954 - 1160 páginas
...Government, acts of another contractor in the Serformance of a contract with the Government, fires, oods, epidemics, quarantine restrictions, strikes, freight...weather or delays of subcontractors due to such causes, if the contractor shall within 10 days from the beginning of any such delay (unless the contracting...
Visualização integral - Acerca deste livro

Cases Decided in the United States Court of Claims ... with ..., Volume 131

United States. Court of Claims, Audrey Bernhardt - 1955 - 908 páginas
...due to unforeseeable causes beyond the control and without the fault or negligence of the contractor, including, but not restricted to, acts of God, or of the public enemy, acts of the Government, acts of another contractor in the performance of a contract with the Government, fires, floods, epidemics,...
Visualização integral - Acerca deste livro

Cases Decided in the Court of Claims of the United States, Volume 111

United States. Court of Claims - 1948 - 886 páginas
...due to unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including, but not restricted to, acts of God, or of the public enemy, acts of the Government or any state or political subdivision thereof (including, but not restricted to the operation of any...